Eighteen Months of Built-Surface Monitoring at a Grünheide Factory Site
A monthly Sentinel-2 built-surface record for a factory site in Grünheide, Brandenburg, from February 2021 to July 2022, with 44.2 per cent of the site and 48.0 per cent of the planned footprint read as built by June 2022.
- Location
- Factory site, Grünheide, Brandenburg
- Scope
- Whole site and a drawn planned footprint
- Record
- 18 months (February 2021 to July 2022)
- Deliverables
- Monthly built-share table, true-colour images, built-ground map layer, radar series
The problem
A construction lender releases funds against progress and needs a dated monthly reading of the site between draw requests without a monthly site visit.
What we did
The share of the site reading as built surface, from one Sentinel-2 composite per calendar month, with the clear-look count printed beside each figure.
The result
17 of 18 months read, with 44.2 per cent of the site and 48.0 per cent of the planned footprint built by June 2022.
The Objective
Construction lenders release funds against progress. The contractor's report states how far the build has advanced; the lender requires an independent, dated reading of the ground to set beside it before each drawdown. A builder's risk insurer requires the same reading to establish what stood on the site in a given month. Monthly site visits across a book of builds in several countries are slow and costly, and on a large site a visit captures one day rather than a series.
Monthly Built-Surface Measurement
The site at Grünheide, south-east of Berlin, went from cleared forest in mid-2020 to a largely complete factory shell by mid-2022. The platform registered the site with a start date of 1 June 2020 and read the trailing 18 calendar months ending 1 July 2022, a window that matches the life of a build and a lender's drawdown schedule. Inputs:
- One Copernicus Sentinel-2 composite per calendar month.
- The built-up index published by Zha, Gao and Ni (2003), applied under the same rule every month so the series is comparable from one month to the next.
- A planned footprint drawn inside the site, read a second time so the record reports the built share of the footprint alongside the whole site.
- Sentinel-1 radar for the first and the latest month, printed beside the series as a weather-independent second line.
To ensure each monthly figure can be weighed correctly, the system prints the number of clear looks behind it, from 1 to 8 per month.

Construction Progress Findings
The pipeline returned a clear reading for 17 of 18 calendar months.
- February 2021: 39.6 per cent of the site built, 49.5 per cent of the footprint, on 2 looks.
- April 2021: 50.4 per cent of the site, 55.1 per cent of the footprint, on 3 looks.
- March 2022: 47.4 per cent of the site, 48.6 per cent of the footprint, on 8 looks.
- June 2022: 44.2 per cent of the site, 48.0 per cent of the footprint, on 8 looks.
- From March 2022, with six to eight looks per month, the site series held between 41.5 and 47.4 per cent.

The footprint read higher than the whole site in every month. It excludes the unbuilt perimeter and access roads that the whole-site figure carries, which gives a lender a sharper series when the plan is sent with the boundary. The June 2022 figures are consistent with a site substantially built but not yet finished, the publicly documented state of the site at that date.
True-Colour Image Record
The record pairs the series with true-colour imagery for the first and most recent months. In February 2021 the main hall stands in cleared ground with ploughed land to the north. By June 2022 the buildings beside it are up and the open ground to the north is paved.

Operational Utility
The lender sets the dated monthly series beside the contractor's progress report. When a drawdown request and the ground disagree, the lender has a dated scene to put in front of the contractor before funds move. A builder's risk insurer holds a dated record of when the main structures stood and when the open ground was paved, on file before any loss is reported. Each site returns a monthly table of built share for the site and the footprint with clear-look counts, a true-colour image for each of the six most recent months, a map layer of built ground for the latest month and a radar figure for the first and latest months. Once the build completes, the site moves onto the Asset Status Check.
Run this on your own ground
Draw an area of interest, pick the dates, and the same analysis runs against the archive over your sites.
References
- Axine Labs (2026). Dated records for claims and portfolios. The products, and three live runs, section 2.
- Zha Y., Gao J., Ni S. (2003). Use of normalized difference built-up index in automatically mapping urban areas from TM imagery. International Journal of Remote Sensing 24(3), 583 to 594.
- European Space Agency. Copernicus Sentinel-2 mission. sentinels.copernicus.eu
More case studies

Storm Johannes Stand Ranking From Sentinel-1 and Sentinel-2 Across 323 Swedish Conifer Stands
A post-storm ranking of 323 one-hectare conifer stands in central Sweden, each read from Sentinel-1 and Sentinel-2 against its own quiet years and scored against Copernicus EMS grading.

Forty-Three Seasons of a Nebraska Pivot and Management Zone Delineation
A 43-year canopy baseline for one centre pivot near Seward, Nebraska, and a three-tier management zone map built from vegetation, terrain and radar moisture.

Season Brief and Fourteen-Day Disease Forecast for a Kansas Corn Pivot
A 184-day season brief for a 61-hectare corn pivot in western Kansas against its own 10-year normal, with five published disease models run on the field's own 14-day forecast.


